Fire Damage, Burton

69 Berry Hedge

A large hole in the roof was previous covered during mitigation works undertaken by Bonsers

The roof had a large hole of around 3m x 2m that had to be made water tight during the initial surveying and pricing process.

The roof had a large hole of around 3m x 2m that had to be made water tight during the initial surveying and pricing process.

Bonser Building Contractors were appointed as the contractor via Bedford Surveyors for fire reinstatement works that left a semi-detached property within the town of Burton upon Trent requiring complete internal repairs along with roof structure repairs and a new covering. Mitch was appointed as the main principal contractor on the behalf of Bonser Building Contractors, The works began in October with the general strip out of the property and the roof works to ensure the safety of the property to any persons internally and the neighbouring properties.

Due to the extent of the fire, the majority of the first floor structure and covering also needed repairing, these works were undertaken prior to any major internal reinstatement works.

The works are still progressing at this stage and further information will be added as the works progress / near completion.